A NEWSLETTER FROM ADVANCED ENERGY UNITED |
|
| |
|
|
This month’s bulletin looks at PJM’s mounting urgency across reliability, affordability, and governance. Recent federal decisions have delayed key plans for managing large-load growth, deepening uncertainty about how PJM will add urgently needed resources while protecting existing customers. At the same time, tightening supplies, market redesign efforts, interconnection reforms, and expanded state coordination remain in focus. Together, these developments highlight the increasingly complex decisions facing PJM, FERC, and state leaders; and underscore the need for swift, coordinated action to bring new resources online, protect consumers, and strengthen confidence in PJM’s decision-making.
|
|
|
|
FERC Rejects Much of PJM’s Plan to Manage Data Center Influx, Creating More Delay and Uncertainty
|
On October 9, FERC rejected PJM’s Interim Resource Adequacy Service (IRAS) proposal after FERC sent back much of PJM’s Reliability Backstop Procurement (RBP) proposal on September 29, significantly delaying the planned procurement of urgently needed new resources and creating more uncertainty as to what’s next. PJM has spent over a year developing these plans, which together were designed to allow data centers and other large loads onto its system without adversely impacting existing customers, despite PJM being short on generation. FERC had criticized PJM for not moving fast enough in “meeting the moment” when it directed PJM to conduct the RBP by September, and now FERC’s decision will delay these urgently needed processes.
On RBP, FERC’s decision will delay, but ultimately not stop, the planned backstop procurement. FERC’s Order on RBP raised concerns regarding cost allocation, provisions in the event of a transmission owner existing PJM, and demand collateral. The Commission laid out two paths forward: PJM could re-file the proposal, addressing the concerns FERC raised in its order, or undergo a paper hearing. PJM announced they will hold a special Markets Committee (MC) meeting on October 22 to vote on an anticipated October 29 FERC 205 filing on PJM’s RBP response. PJM is “considering the possibility” of running the RBP before February 2027, and will discuss their latest thinking at the October 22 special MC. Even if PJM sticks to that timeframe, the delay caused by FERC’s rejection and PJM’s re-filing will push the RBP to after the upcoming 2029/30 BRA scheduled for December, meaning that PJM will also have to reshuffle the interaction between the RBP and the BRA.
On IRAS, next steps are less clear because FERC’s decision identified problems with the filing but left it up to PJM to figure out whether and how to fix them. In rejecting the IRAS plan, FERC was focused on jurisdictional grounds, discriminatory curtailment, and accreditation of bring your own new capacity resources. PJM’s proposed IRAS framework would have encouraged new large loads to bring matching new capacity by subjecting them to risk of curtailment in the event of grid supply emergencies if they failed to do so.
FERC’s order approved PJM’s large load definition and the creation of a large load registry, but rejected the IRAS portion of the filing, stating that the proposal would intrude on state jurisdiction over retail rates and that it appears to discriminate against certain firm loads without adequate justification. PJM is regulated at the federal level by FERC, and retail customers and rates (including data centers) are regulated at the state level. PJM tried to avoid jurisdictional landmines by placing obligations on Electric Distribution Companies and Load Serving Entities rather than individual retail customers, but FERC found that the PJM plan intruded into state jurisdictional authority. FERC stated in the order: “We find that several provisions of the proposed tariff appear to place obligations directly on eligible new large loads, which are, for the most part, retail customers; that certain other provisions appear to dictate which retail customers taking retail service will be curtailed; and that the proposed compensation framework appears to establish a retail rate.” FERC also pointedly reminded states that they have, “a crucial role to play in this challenge by designating which retail customers must be curtailed when the system is stressed,” and said that “we strongly encourage states to continue their important work on this issue.”
FERC and PJM have both been clear that they want reliable, affordable power in PJM as quickly as possible, while simultaneously allowing data center development to move forward. What is not clear at this time is when and how PJM will move forward in the wake of FERC’s IRAS decision. It appears likely that states will be tasked with taking on a larger role in managing data center load and curtailment, which will require unprecedented coordination across PJM states and between PJM and the states. Whatever happens, it needs to happen quickly, because the longer the current uncertainty and delay persists, the longer it will take to get new generation developed and online, which is something we can’t afford right now.
|
|
| |
PJM Updates & Policy Developments |
|
|
PJM Fails to Reach Consensus with States on Governance Reforms, Leaving Reform Process in FERC’s Hands
In a special meeting of the PJM Members Committee on September 30, PJM members voted on three governance proposals that emerged from the sequestered FERC PJM governance mediation process that ended the same day. This vote was the culmination of a process that began as follow up to the July 23 technical conference convened by FERC focused on governance and reforms at PJM. The conference was followed by a FERC ordered facilitated dispute resolution mediation in September where PJM stakeholders were given until the end of the month to reach consensus on a governance reform package. Areas for reform discussed included: PJM board independence; transparency; state participation in PJM; State filing rights at FERC; and stakeholder voting rights. FERC Chair Swett indicated that if an agreement wasn’t reached by the end of September, FERC would impose its own reforms on PJM.
The PJM staff proposal and the state consumer advocates’ proposals did not receive the required PJM membership majority votes to pass. Somewhat unsurprisingly, the PJM members’ proposal received a significant passing majority. The PJM state governors were not part of the FERC mediation and were not able to develop their own proposal in this process (states were only represented by consumer advocates), but state governors’ representatives at the meeting made it clear ahead of the vote how disappointed they were with the member proposal which later passed, which state representatives at the meeting characterized as giving states no additional stake in PJM governance over the status quo. While the members’ proposal did give the states some nominal say (such as a seat on the nominating committee), it fell short of granting the states independent jump-ball filing rights.
The member vote was indicative, so next steps were in the hands of the PJM Board of Managers, who had hoped to reach consensus with the states rather than leaving it to FERC to rule unilaterally on the PJM governance structure as they have already threatened to do. The PJM board filed a letter along with the member approved term-sheet at FERC late on September 30, meeting FERC’s deadline. Given the states’ vehement opposition to the PJM member plan, next steps from FERC are unclear at this time. While it appears likely that stakeholders will be demoted within the PJM governance structure, it remains unclear whether the stakeholder process will become purely advisory (like MISO) or if stakeholders will retain some filing rights (potentially jump-ball rights, like in ISO-NE). And while states seem to be poised to gain power within PJM, what that looks like and how it’s split among different state entities is also uncertain.
|
All PJM Governors Sign on to MOU Formally Establishing the PJM Governor’s Collaborative – October 6th Chicago PJM Governors' Summit on PJM
The PJM Governors' Collaborative held its 2026 Governors' Summit on PJM on October 8 in Chicago. This summit follows the inaugural PJM Governors' Collaborative held last year in Philadelphia, which focused on PJM governance and reliability concerns. This Summit marked the formal launch of the bipartisan multi-state PJM Governors’ Collaborative with the governors agreeing to a memorandum of understanding that brings together 13 governors and the mayor of Washington, D.C., to present a unified front as part of a broad effort to reform PJM’s governance and decision-making processes. Officials said the Collaborative will give states a place to work together on issues involving PJM Interconnection by allowing governors and their staffs to share information, develop joint positions on PJM issues, and coordinate with PJM, the Federal Energy Regulatory Commission, state utility commissions and other energy-policy organizations. Illinois Gov. JB Pritzker in his keynote address at the summit said: “Families in Illinois and across the region deserve more from PJM, and as Governors, we refuse to sit by idly as they prioritize profits over people."
|
Show Cause 2026 Co-Located Load Order Compliance
PJM previewed its conceptual approach to interconnection queue reforms driven by the FERC Show Cause proceeding** at PJM’s July 31 PJM Co-Located Load Order Workshop. According to PJM, generation interconnection, transmission interconnection, long term firm requests, and new large load would be studied cohesively to determine the most efficient solution for the cluster.
While studying load and generation in a single, consolidated planning process is promising in theory, significant concerns have been raised about the proposal by project developers and market participants. After members expressed significant concern with the initial proposal, PJM developed and presented a revised Show Cause integrated interconnection proposal at a September 16th workshop and provided manual tariff redlines at an October 16th workshop that failed to alleviate many stakeholder concerns detailed below:
New stringent site control rules and significantly higher security postings could have a chilling effect on new project proposals. While a high bar to entry is necessary to reduce speculative projects, PJM has already increased entry requirements as part of its 2022 interconnection reforms.
A faster process that does not provide greater upfront certainty could likely introduce more risk for developers and lead to more withdrawals and restudies, not fewer. Moving toward more holistic planning and a faster process is good, but it must be done in a way that increases upfront certainty, similar to the Southwest Power Pool (SPP) Consolidated Planning Process (CPP) with an entry fee model (which is also a proposed requirement under the newly introduced Bipartisan American Affordability and Jobs Act, BAAJA).
Moving large loads into the generator interconnection process is not full holistic and proactive long-term planning; simply adding additional projects into the interconnection process could result in cost shifts and introduce more uncertainty, interdependency, and withdrawal risk that would slow down the process, raising questions about the ability to achieve the promised 12-month study process.
Many of these issues were articulated in the October 2 Corporate Energy Buyer’s Association (CEBA) and the Data Center Coalition (DCC) Joint letter to the PJM Board of Managers. PJM faces a November 16th filing deadline at FERC, meaning that this major overhaul of its interconnection process is moving forward at warp speed, leaving little time to work through critical elements like cost allocation and entry requirements.
|
**On December 18, 2025, in Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000, the Commission issued an order finding that PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load. The Commission found specifically that PJM’s Tariff does not include types of transmission service that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their use of the transmission system under certain conditions. Additionally, the Order determines that PJM’s existing Behind the Meter Generation rules have become unjust and unreasonable because they raise reliability and resource adequacy risks and are inconsistent with cost causation. The Commission additionally ordered PJM to make several compliance filings to revise its Tariff accordingly and ordered PJM to submit an informational report within 30 days of the order. The Commission also set certain matters for paper hearing, and established a paper hearing schedule. The Commission directed PJM to submit several filings, with the first compliance filing and informational report due on January 20, 2026. Other compliance filings and paper hearing submissions are due starting on February 17, 2026.
|
Unusual PJM October Maximum Generation Alert Another Indicator of Potential PJM Reliability Concerns
In an unusual move, PJM issued a “Maximum Generation Alert and Load Management Alert” for October 13 and 14. PJM alerted power plant owners and electric utilities October 12 of the need to take steps to avoid rolling blackouts as the demand for power approaches the grid’s current maximum capacity. It called on them to suspend maintenance and keep generators online where possible to ensure the grid remains stable. It’s unusual to have an energy emergency in the autumn, when moderate weather causes electricity demand to ease – PJM’s response is just another indicator of the tightening of supply on the system where a routine seasonal maintenance is now an emergency, and PJM’s ongoing struggle to bring needed generation online quickly.
In a letter to the DOE on Sunday requesting the emergency measures, PJM warned that due to the combined effects of increased demand, maintenance and significant export obligations, the grid is expected to be within 900 megawatts of its reserve margin. That’s roughly the equivalent of a single large power plant. PJM said electricity demand is increasing faster than new generating capacity can be added to the system, while unpredictable weather patterns are reducing the time available for maintenance.
The tightening supply also has environmental consequences, PJM requested and received an emergency order, effective from Oct. 13–16, from the U.S. Department of Energy. The 202c order grants PJM operators additional flexibility to respond to changing system conditions by providing temporary relief from environmental permit emissions restrictions for generating units, and authorizing PJM to direct data centers and other Large Load customers to switch to backup generation resources (typically diesel generators) if necessary.
|
PJM’s Holistic Market Redesign – workshops
PJM’s CEO acknowledged early in 2026 that the current capacity market construct is not working in today’s high demand growth environment that is also characterized by longer siting and construction timelines. PJM announced a holistic market redesign process and issued a whitepaper on May 6th (Powering Reliability Through Market Design) articulating market flaws. Shortly thereafter, PJM kicked off a "holistic market redesign" effort that has included a series of stakeholder workshops and a request for stakeholder papers/comments. Among other organizations, United filed written comments and presented recommendations at an October 1-2 PJM stakeholder workshop.
OPSI provided feedback to PJM on October 16, including reactions to PJM’s three proposed paths as well as recommendations for near-term priority reforms. Overall, OPSI encouraged PJM to facilitate, but not require, long-term hedging, and cautioned against differential reliability (except through a “durable framework” for prioritized curtailment of certain large loads where resource adequacy cannot be met). OPSI urged against abandoning PJM’s capacity market construct, while remaining open to moving more revenue into energy and ancillary services markets if done thoughtfully and slowly, not as an immediate reliability solution. In the near-term, OPSI urged progress on adoption of a seasonal capacity construct, reforming performance penalties, stabilizing ELCCs, expediting generator interconnection, and conducting holistic planning for transmission and generation solutions.
PJM has indicated that the Board will develop proposals and scope, followed by additional November workshops and a formal stakeholder process in early 2027. |
PJM Membership Elects Janet Dietrich to Board of Managers
PJM Interconnection announced on September 24 that its members elected Janet Dietrich to the PJM Board of Managers, effective immediately. Dietrich fills the remainder of the term of David Mills, which expires in May 2027, at which time she would be eligible for reelection. Mills left the Board in April as he accepted the role of PJM president and CEO. Dietrich is a former energy executive with more than three decades of global leadership experience spanning wholesale and retail energy markets, commodity trading, finance, risk, infrastructure and asset management, and large-scale business transformation. She brings extensive experience in the full energy value chain in both the conventional energy markets as well as the energy transition and lower-carbon solutions. She most recently spent 13 years with Macquarie Group, where she held several senior leadership roles, including Global Head of Energy Transition and Strategy, Head of Corporate Sales Americas, and Co-Head of Oil & Gas Financing Americas. She is a Finance Advisory Board member at the University of Kentucky, Gatton College of Business and Economics, and a board member for The Houston Alumni & Youth (HAY) Center, serving youth aging out of foster care. Dietrich holds a Bachelor of Business Administration in finance from the University of Kentucky. She completed AI coursework at the MIT Sloan School of Management and coursework at The University of Cambridge Judge Business School for Circular Economy and Sustainability Strategies.
|
|
|
|
The Federal Energy Regulatory Commission is an important independent agency that regulates interstate transmission of electricity, natural gas, and oil. As the agency that oversees regional transmission organizations such as PJM, it is important to know what FERC is working on and how this may impact consumers in your state. The following FERC filings and decisions are worth tracking this month. |
“First-ready, First-served" Interconnection Reform- (ER22-2110-000)
On August 14, 2026, PJM filed an informational report providing updates on the processing of New Service Requests under its Transition Period Rules, as required by FERC’s November 29, 2022 order accepting PJM's comprehensive reform of its generation interconnection process. PJM is currently in Phase III of Transition Cycle 2; processing 450 projects, with 270 remaining, and an expected competition date of January 4, 2027. PJM has generally met its timeline targets, with Transition Cycle 2 Phase II completing within the required 180-day period (December 3, 2025 to June 5, 2026). The new Cycle 1 under the reformed interconnection process commenced on April 28, 2026.
|
Complaint of Voluts and Mission:data against PJM (EL26-4-000)
On September 14, PJM filed it’s initial brief in response to a complaint brought by Voltus, and Mission:data. In the brief, PJM responds to 8 specific questions posed by FERC in its July 2026 Order that found potential barriers to the PJM market participation and directed a paper hearing to develop a replacement rate. PJM proposes expanding statistical sampling eligibility to interval-metered residential customers with Direct Load Control and two-way switch communication when Curtailment Service Providers (CSPs) cannot reasonably access interval meter data.
|
Order 1920 Compliance- (RM21-17-000)
On October 8, 2026, FERC issued notice granting a joint motion to extend compliance deadlines for Order No. 1920 on regional transmission planning and cost allocation within the PJM region. PJM TOs now have until November 19, 2026 to file their portion of the regional compliance filing. PJM must submit revisions to its proposed LTRTP Protocol by December 22, 2026. The extensions account for time needed for PJM TOs to draft tariff sheets, for PARSEC to finalize its alternative proposal, and for both parties to complete internal governance votes. For the LTRTP Protocol, PJM needs time to develop its approach, hold a public stakeholder meeting, incorporate feedback, and finalize its filing.
|
|
|
|
Upcoming Events & Engagement Opportunities |
Special Members Committee Meeting- Register Webex | October 22, 9am-12pm
PJM will present and vote on its revised RBP response to FERC, ahead of an anticipated October 29 filing, and discuss timing and coordination with the December 2029/30 capacity auction. |
Powering Reliability Through Market Design Workshops- Register Webex | Nov. 11, 9am-12pm
PJM will continue developing its holistic market redesign, including possible reforms to capacity, energy, and ancillary-services markets. The discussion will inform Board proposals and a formal stakeholder process expected in early 2027. |
Organization of PJM States, Inc. (OPSI) — Annual Meeting Traverse City, Michigan | October 19-22, 2026 Convenes PJM state commissions and consumer advocates to coordinate on transmission planning, cost allocation, and market reforms. |
|
|
- Trump Restricts Import of Bulk Power System Equipment- Utility Dive
-
“The Aug. 26 executive order cites cybersecurity concerns with everything from transformers and batteries to substations and inverters, plus much more.”
- PJM has finally greenlit a lot of new clean power. Can it get built?- Canary Media
- “More than 50 GW of solar, wind, and batteries can now connect to PJM’s grid. It could help drive down costs — if states, utilities, and hyperscalers make it happen.”
-
PJM’s reliability could start failing by 2030 if data center growth continues- Utility Dive
-
“In a worst-case scenario, the modeled loss of load expectation is “over 100 times worse than PJM’s planning criterion,” indicating an expectation of “more than 13 days with loss of load events per year,” said the study commissioned by the Pennsylvania PUC."
-
PJM Interconnection issues alerts warning of tight electricity supplies- Yahoo News
-
“PJM Interconnection alerted power plant owners and electric utilities Monday of the need to take steps to avoid rolling blackouts as the demand for power approaches the grid's current maximum capacity.”
-
US panel approves PJM's registry of data centers, rejects plan to curtail power to them- Reuters
-
“FERC rejects PJM's temporary curtailment plan to manage data centers; PJM can move forward with data center tracking on October 12; PJM can submit revised curtailment plan with changes”
- FERC rejects most of PJM’s large load interconnection plan- Utility Dive
- “PJM Interconnection’s plan for curtailing large loads that don’t have matching new generation intrudes on state jurisdiction and may be discriminatory, the Federal Energy Regulatory Commission said.”
-
FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction- Utility Dive
|
|
|